The short answer
As of November 26, 2026, an applicant for a commercial SMR or advanced reactor can choose among three NRC rule sets in Title 10 of the Code of Federal Regulations:
- Part 50: a construction permit, then a separate operating license.
- Part 52: a combined license, plus early site permits, design certifications, standard design approvals and manufacturing licenses.
- Part 53: a risk-informed, technology-inclusive framework that offers the same family of permits, licenses and approvals. It took effect on April 29, 2026.
A fourth rule set, Part 57 for microreactors and reactors with comparable risk profiles, is a proposed rule. It is not final. Most applicants also spend months or years in NRC pre-application engagement before they file.
Part 50: the two-step path
Part 50 is the original licensing route. Under 10 CFR 50.23, the NRC issues a construction permit first. When the facility is complete and the Commission acts, the permit is converted into an operating license under § 50.56.
The two-step structure lets construction begin before every design detail is final. The tradeoff is a second major review and decision at the operating license stage.
Part 52: one license, plus design and site approvals
Part 52 is titled “Licenses, Certifications, and Approvals for Nuclear Power Plants.” It offers five tools, each defined in § 52.1:
- Combined license (COL): a combined construction permit and operating license with conditions. The COL lists the inspections, tests, analyses and acceptance criteria (ITAAC) that show the plant was built as licensed (§ 52.97).
- Early site permit (ESP): approval of a site for one or more facilities, defined as a partial construction permit. It is valid for 10 to 20 years (§ 52.26).
- Standard design certification: a Commission approval of a final standard design, issued by rule. It is valid for 40 years from issuance (§ 52.55).
- Standard design approval: an NRC staff approval of a final design, covering a whole facility or major portions of one.
- Manufacturing license: authorizes the manufacture of reactors, but not their construction, installation or operation at the sites where they will run.
A COL application can reference a certified design and an early site permit, so issues resolved earlier are not reopened in the same way.
Part 53: the risk-informed framework
The NRC published Part 53 as a final rule on March 30, 2026 (91 FR 15696). It took effect on April 29, 2026. The Nuclear Energy Innovation and Modernization Act required it. Corrections followed on April 13 and July 28, 2026.
Key points from the rule text:
- It is an alternative to Parts 50 and 52, not a replacement. The NRC says it can be used for any reactor technology, any size and any end use.
- Subpart H provides early site permits, standard design approvals, design certifications, manufacturing licenses, construction permits, operating licenses and combined licenses.
- Safety requirements are technology-inclusive. Design-basis accidents are analyzed deterministically against a 25 rem reference value. Other licensing-basis events are judged against a comprehensive risk metric with risk performance objectives. Defense-in-depth and Part 20 dose limits also apply.
Part 57: the microreactor proposal
On May 1, 2026, the NRC proposed a new 10 CFR Part 57, “Licensing Requirements for Microreactors and Other Reactors With Comparable Risk Profiles” (91 FR 23628, docket NRC-2025-0379). The notice set a comment deadline of June 15, 2026. A correction was published on May 15, 2026.
The proposal cites section 208 of the ADVANCE Act, which calls for risk-informed and performance-based strategies to license micro-reactors, and section 5(e) of Executive Order 14300, which directs a process for high-volume licensing of microreactors and modular reactors.
As proposed, Part 57 would:
- Admit designs that meet a 1 rem (10 mSv) total effective dose equivalent entry criterion, plus a limit on the quantity of fuel.
- Use a joint application for a construction permit and operating licenses, with final design information and complete operational programs submitted up front.
- Offer manufacturing licenses and standard design approvals.
- Provide a general license for certain construction activities before a construction permit issues, for an “nth-of-a-kind” facility.
The NRC states that it did not pursue a combined license approach in Part 57 because ITAAC were designed for light water reactors. As of November 26, 2026, the Federal Register shows the proposed rule and its correction, but no final rule. The NRC’s EO 14300 rulemaking table plans the final rule for January 26, 2027.
Pre-application engagement
The NRC’s pre-application process page says pre-application activities mainly occur through three processes, and that applicants should develop a regulatory engagement plan. The tools are:
- White papers and technical reports: white papers request feedback on technical, programmatic, regulatory or administrative topics. Feedback comes as staff observations. It contains no regulatory findings, is not an agency position and cannot be cited as pre-approval.
- Topical reports: these seek NRC review and approval of a single, critical technical issue through a safety evaluation. If a later application meets the report’s limitations and conditions, staff will not re-review that subject.
- Readiness assessments: voluntary reviews of a draft application that identify information gaps and major issues. The results go into a report, but the assessment does not predetermine whether the NRC will accept and docket the application.
- Regulatory engagement plan: the applicant’s plan for its interactions with the NRC.
The NRC also describes a letter of intent that requests a project number, a kickoff public meeting and a public outreach meeting near the proposed site.
Review timelines in statute and executive order
- ADVANCE Act section 207 (Pub. L. 118-67, Division B) sets an expedited COL procedure for applications that reference a certified design or a substantially similar licensed design, on a site where a licensed commercial reactor operates or previously operated, or directly adjacent to one. To the maximum extent practicable, the NRC is to issue the safety evaluation and environmental document within 18 months of docketing and make a final decision within 25 months.
- Executive Order 14300 directs the NRC to set a deadline of no more than 18 months for a final decision on an application to construct and operate a new reactor.
- Contested hearings. A final rule published November 3, 2026 (91 FR 69446), effective December 3, 2026, streamlines contested adjudications in licensing proceedings under the ADVANCE Act and EO 14300.
What to watch
- A final Part 57 rule, and how it treats the 1 rem entry criterion, the fuel limit and construction before a permit.
- The NRC’s proposed rule modernizing reactor licensing, safety oversight and siting (docket NRC-2025-0975), which would amend Parts 50, 52 and 53. Comments closed August 31, 2026.
- The final rule on reviews of designs previously authorized by DOE or the Department of War, published October 26, 2026 and in effect since November 25, 2026. It amends Parts 50 and 53.
- Guidance that accompanies Part 53 and the first applications filed under it.
Operon follows licensing activity across these pathways in its briefings.
Primary sources
- Streamlining Contested Adjudications in Licensing Proceedings, final rule (November 3, 2026)
- 10 CFR Part 50, § 50.23 (eCFR)
- 10 CFR Part 52 (eCFR)
- 10 CFR Part 53 (eCFR)
- Part 53 final rule, 91 FR 15696 (March 30, 2026)
- Part 53 correction (July 28, 2026)
- Part 57 proposed rule, 91 FR 23628 (May 1, 2026)
- Modernizing Reactor Licensing, Safety Oversight, and Siting Practices, proposed rule (July 16, 2026)
- NRC Reviews of Reactor Designs Previously Authorized by DOE or DoW, final rule (October 26, 2026)
- Executive Order 14300, Ordering the Reform of the Nuclear Regulatory Commission
- Public Law 118-67, including the ADVANCE Act of 2024
- NRC: Pre-application process for advanced reactors