The short answer
The ADVANCE Act of 2024 became law on July 9, 2024, as Division B of Public Law 118-67. It gives the Nuclear Regulatory Commission (NRC) a long list of reports, rule changes and process reforms, most with deadlines counted from that date.
As of November 26, 2026, the NRC has adopted a new mission statement, cut the hourly fee for advanced reactor applicants, finished a rule on foreign ownership, and sent Congress most of the reports the Act requires. The main open items are the microreactor framework and the brownfield licensing strategy, with statutory deadlines that run to July 2027.
One point often gets blurred. The Act itself sets no November 2026 deadline for final rules. That date comes from Executive Order 14300, which told the NRC to issue final rules within 18 months of May 23, 2025.
What the law requires of the NRC
The Act runs to six titles. These are the provisions that matter most for reactor developers and investors.
Mission statement (Section 501)
Within one year, the NRC had to update its mission statement so that licensing is “efficient” and does not unnecessarily limit the civilian use of nuclear energy. It then had to report the new statement and its staff guidance to Congress.
Lower fees for advanced reactors (Section 201)
The Act caps the hourly rate the NRC charges advanced reactor applicants and pre-applicants at the cost of mission-direct staff time, leaving out overhead. The cap took effect on October 1, 2025. The pre-applicant cap expires on September 30, 2030.
Licensing prizes (Section 202)
The Act authorizes prizes for the first advanced reactors licensed in several categories, such as the first to use spent fuel or depleted uranium as fuel. The prize equals the NRC fees the winner paid. Note that the Secretary of Energy, as NEIMA defines the term, makes these awards, not the NRC, and only if Congress appropriates the money.
Faster combined license reviews (Section 207)
The NRC must run an expedited review for combined license applications that use a certified or already licensed design and sit on or next to an existing or former reactor site. The targets, “to the maximum extent practicable,” are a safety evaluation and environmental document within 18 months of docketing, hearings within 2 years, and a decision within 25 months. Missed deadlines must be reported to the Commission, and to Congress after 90 days.
Microreactors (Section 208)
The NRC had 18 months to develop risk-informed strategies and guidance for microreactors, covering staffing, security, emergency planning, transport of fueled units and siting. It has 3 years, until July 9, 2027, to put them in place through existing rules, the new technology-inclusive framework or a rulemaking.
Brownfield and retired fossil sites (Section 206)
The NRC had one year to assess what changes would speed licensing at brownfield and retired fossil fuel sites, and 14 months to report. Within 2 years it had to adopt strategies or start a rulemaking. A report on those actions is due within 3 years.
Foreign ownership (Section 301)
The Atomic Energy Act bars licensing reactors owned, controlled or dominated by foreign interests. Section 301 lifts that bar for entities tied to OECD member countries and India, excluding countries under certain sanctions, if the NRC finds the license is not inimical to security or public health and safety. It leaves CFIUS review untouched.
Environmental reviews (Section 506)
Within 180 days, the NRC had to report on making environmental reviews faster. The report had to weigh categorical exclusions, environmental assessments, generic impact statements and changes to 10 CFR Part 51, and include a schedule for any needed rule.
Other duties
The Act also covers fusion machine regulation (Section 205), advanced fuel qualification with the Department of Energy (Section 404), oversight and inspection reform (Section 507) and licensing efficiency (Section 505). Section 505 directs the NRC to reuse an existing site’s licensing basis where practicable.
What the NRC has done
The NRC lists its submissions on its ADVANCE Act related documents page. Highlights:
- Mission statement. The NRC adopted a new mission statement that speaks of “enabling the safe and secure use and deployment of civilian nuclear energy technologies.” It sent Congress its mission alignment report on November 18, 2025.
- Fees. The FY 2025 fee rule set a reduced rate of $148 an hour from October 1, 2025. The FY 2026 fee rule, effective August 17, 2026, raised it to $154. The NRC says that is over 50 percent below its $337 professional rate.
- Foreign ownership. A direct final rule published April 23, 2026 wrote the Section 301 exceptions into the NRC’s rules. The NRC confirmed it took effect July 7, 2026.
- Reports to Congress. The page lists reports on environmental reviews and on advanced manufacturing (January 6, 2025), nonelectric uses (May 1, 2025), fusion and oversight reform (July 10, 2025), brownfield sites (August 25, 2025) and advanced fuel (June 29, 2026).
- Fuel coordination. The NRC and DOE signed their advanced fuel memorandum of understanding on December 12, 2024.
- Combined license reviews. The NRC issued Regulatory Issue Summary 2026-04, “Combined License Review Performance and Reporting,” listed under Section 207 on April 27, 2026.
- Microreactors. On May 1, 2026, the NRC proposed a new Part 57 for microreactors and similar low-risk reactors. Comments closed June 15, 2026.
- Brownfield guidance. The NRC posted considerations for applicants at brownfield and retired fossil sites. The page cites Section 206 and EO 14300.
Separately, the NRC’s Part 53 technology-inclusive framework took effect April 29, 2026. Part 53 implements the earlier NEIMA law, not the ADVANCE Act. Even so, one ADVANCE Act prize category is tied to it.
How the NRC reports progress: the ADVANCE Act dashboard
The NRC runs an ADVANCE Act Status Dashboard. It shows each tasking by section of the Act, the lead office, deliverable dates and staff contacts. The NRC notes that its downloadable Excel data “may be outdated” next to the live dashboard. The page was last updated October 1, 2026.
The NRC does not publish a headline count of completed actions on these pages, and this guide does not cite one. The Office of the Executive Director for Operations coordinates implementation and the reports to Congress.
Deadlines still ahead
Counted from enactment on July 9, 2024:
- January 9, 2026 (passed). Microreactor strategies and guidance due under Section 208(a)(1). Check the dashboard for the NRC’s own status.
- July 9, 2026 (passed). Brownfield strategies, or the start of a rulemaking, due under Section 206(c). Check the dashboard here too.
- July 9, 2027. Microreactor strategies must be in place under Section 208(a)(2). The brownfield actions report is due under Section 206(d).
- Every 3 years. The NRC must review its NEIMA performance metrics and milestone schedules (Section 504).
- September 30, 2030. The reduced fee for pre-applicants expires (Section 201).
The executive order’s 18-month mark fell on November 23, 2026, with most of the revision still open. In the weeks before it the NRC finished three rules: reviews of designs already authorized by DOE or the Department of War (final rule, October 26, effective November 25), streamlined contested hearings (November 3, effective December 3), and a direct final rule that narrows the Advisory Committee on Reactor Safeguards to its statutory minimum (November 17; it takes effect February 1, 2027 unless significant adverse comments arrive by December 17). The NRC’s EO 14300 rulemaking table now plans the remaining final rules from December 2026 to September 2027. Part 57 is listed for January 26, 2027, the NEPA rule (Part 51) for February 17, 2027, and the reactor licensing and siting rule for February 26, 2027.
What to watch
- Whether the NRC finalizes Part 57 before the July 9, 2027 microreactor deadline.
- What the dashboard reports for the Section 206(c) brownfield strategy and the Section 208(a)(1) microreactor guidance.
- The first combined license application to use the Section 207 expedited track, and any delay reports to Congress.
- The proposed FY 2027 fee rule, which will reset the reduced hourly rate.
- The remaining EO 14300 final rules, now planned through September 2027, including the Part 51 environmental rule (February 2027) and the reactor licensing and siting rule (February 2027).
- Whether the ACRS direct final rule draws significant adverse comments by December 17, 2026, which would send it back through the companion proposed rule.
- Any appropriation for the Section 202 prizes.
Operon tracks ADVANCE Act rulemakings and deadlines in its briefings.
Primary sources
- Public Law 118-67, Division B (ADVANCE Act of 2024), GPO
- S.870, 118th Congress, Congress.gov
- NRC: About the ADVANCE Act
- NRC: ADVANCE Act Status Dashboard
- NRC: ADVANCE Act related documents
- NRC: Wholesale revision of regulations under EO 14300
- Federal Register: FY 2025 fee rule
- Federal Register: FY 2026 fee rule
- Federal Register: Exceptions from foreign ownership, control, or domination
- Federal Register: Proposed Part 57 microreactor rule
- Federal Register: Streamlining contested adjudications, final rule (November 3, 2026)
- Federal Register: Advisory Committee on Reactor Safeguards functions, direct final rule (November 17, 2026)
- Federal Register: Executive Order 14300
About this guide. Written from primary sources, each linked in the text. It describes the rules and programs; it is not legal advice. If something here is wrong or out of date, tell us and we will correct it with a dated note.