DOE Money for New Nuclear: EDF Loans, HALEU and the Reactor Pilot

By As of Last reviewed 11 min read

The short answer

The Department of Energy (DOE) supports new nuclear through three separate programs. Each one gives something different.

  • Debt. The Office of Energy Dominance Financing (EDF), previously the Loan Programs Office (LPO), lends to or guarantees loans for large energy projects. In 2026 it closed or conditionally committed billions of dollars for nuclear restarts, uprates and AP1000 supply chains.
  • Fuel. The HALEU Availability Program allocates high-assay low-enriched uranium from DOE stocks to developers who cannot yet buy it commercially. DOE has made three rounds of conditional commitments.
  • A testing pathway. The Reactor Pilot Program lets companies build and run test reactors under DOE authorization instead of an NRC license. DOE counted four DOE-authorized reactors at criticality by July 6, 2026, against a goal of three by July 4, and a fifth in August.

The loan office: Office of Energy Dominance Financing

What it is

EDF’s home page says the Loan Programs Office “operates as the Office of Energy Dominance Financing.” If you are searching for the Loan Programs Office’s new name, this is it. The office finances energy and manufacturing projects through loans and loan guarantees.

When the name changed

The change came in two steps.

  • October 28, 2025. An interim final rule (90 FR 48705) renamed section 1706 projects from “Energy Infrastructure Reinvestment” to “Energy Dominance Financing.” The statutory heading of section 1706 did not change. The rule still names the “Loan Programs Office” as the administering office.
  • November 20, 2025. DOE’s organization chart, released with a department realignment, lists the “Office of Energy Dominance Financing (EDF).” DOE’s January 22, 2026 release describes the office as “previously known as the Loan Programs Office (LPO)” with “more than $289 billion in available loan authority.”

The office runs loan programs under Title XVII of the Energy Policy Act of 2005 (42 U.S.C. 16511 et seq.). The One Big Beautiful Bill Act, Public Law 119-21, section 50403, amended section 1706. According to the October 2025 rule, DOE may now guarantee section 1706 loans “of up to a total principal amount of $250 billion through September 30, 2028.” EDF’s page describes the Energy Dominance Financing Program as the section 1706 program, which “guarantees loans to projects that add energy to the grid or enhance reliability.” It lists “reinvigorating the nuclear industry” among its priorities.

How companies engage

  • Request a no-cost pre-application consultation with EDF staff.
  • Submit a Part I application, then a Part II application, following EDF’s published instructions.
  • Go through due diligence. EDF says this “typically takes a minimum of six months to more than a year.”
  • According to EDF’s Title 17 FAQs, there is no application fee. Applicants pay third-party advisor costs, a facility fee and annual maintenance fees. Guarantees are “typically $500 million or more,” and EDF can guarantee up to 80% of eligible project costs.

A conditional commitment is not a loan. Before any money moves, the borrower still has to meet technical, legal, environmental and financial conditions.

Energy Dominance Financing for nuclear: loans and commitments

  • Palisades, Michigan. In September 2024, DOE closed a $1.52 billion loan guarantee to Holtec Palisades, LLC to restart the 800 MW plant. The restart is subject to NRC approvals.
  • Crane, Pennsylvania. On November 18, 2025, DOE closed a $1 billion loan to Constellation to restart the 835 MW Crane Clean Energy Center.
  • Southern Company. On February 25, 2026, EDF closed a $26.5 billion loan package to two Southern Company subsidiaries. It covers more than 16 GW of firm power, including 6 GW of nuclear capacity improved through uprates and license renewals.
  • AP1000 supply chain. On June 23, 2026, EDF issued $17.5 billion in conditional commitments under the American Nuclear Supply Chain Loans. The loans would finance long-lead components for 10 Westinghouse AP1000 reactors: five projects, two units per site. Each project requires $1 billion in equity up front.
  • Duane Arnold, Iowa. On September 8, 2026, EDF closed a loan of up to $1.9 billion to NextEra Energy to restart the 615 MW plant. The restart is pending NRC approvals.
  • Vistra fleet. On October 5, 2026, EDF made a conditional commitment of up to $4.2 billion to Vistra for uprates and modernization at Beaver Valley, Davis-Besse and Perry. The work would add 433 MW and preserve about 4 GW. The commitment also includes an option for future uprates at Comanche Peak.
  • Constellation fleet. On October 27, 2026, EDF made a conditional commitment of up to $5 billion to Constellation for uprates and modernization at eight plants in Illinois, Maryland and Pennsylvania, adding nearly 1.1 GW.

The DOE HALEU Availability Program

What it is

HALEU is uranium enriched above 5% and below 20% uranium-235. Many advanced reactor designs need it. DOE says HALEU “is not currently available from domestic suppliers,” so the program allocates material from DOE and NNSA stocks to bridge the gap.

  • Section 2001 of the Energy Act of 2020 (42 U.S.C. 16281) requires DOE, through the Office of Nuclear Energy, to run a program supporting HALEU availability for civilian research, development, demonstration and commercial use.
  • Section 3131(h) of the FY2024 NDAA requires DOE to prioritize HALEU for the two Advanced Reactor Demonstration Program Pathway 1 projects (X-energy and TerraPower). It also directs DOE to seek to make 21 metric tons available by June 30, 2026.
  • Both laws limit releases to material not needed for national security.

These provisions are summarized in DOE’s HALEU Allocation Process. The statutory definition of HALEU is restated in a 2024 Federal Register notice.

How companies engage

Under the allocation process, a company emails a request form to DOE. The form covers quantity, enrichment, form, delivery dates, use, schedule, regulatory status and financing. DOE then weighs five things:

  • links to DOE programs or cost-shared agreements
  • fit with DOE missions
  • schedule maturity
  • the requester’s ability to use the material
  • what DOE actually has in inventory

Approved requesters must sign contracts, hold an NRC possession license, and arrange transport, storage and fabrication before any material moves. DOE can rescind allocations after significant delays.

Allocation rounds

  • Round 1, April 9, 2025. TRISO-X, Kairos Power, Radiant Industries, Westinghouse and TerraPower. DOE received requests from 15 companies.
  • Round 2, August 26, 2025. Antares Nuclear, Standard Nuclear (TRISO fuel lines), and Abilene Christian University with Natura Resources (a molten salt research reactor in Texas).
  • Round 3, July 23, 2026. NASA, for the SR-1 Freedom mission to Mars, and Radiant, for a microreactor at Buckley Space Force Base, Colorado.

DOE has not published quantities for individual recipients. It says the program is ongoing.

The DOE Reactor Pilot Program

What it is

The Reactor Pilot Program lets companies build and operate test reactors outside the national laboratories under DOE authorization, not an NRC license. Companies pay all costs, from design through decommissioning. DOE describes it as a pathway to “fast-track commercial licensing.”

Executive Order 14301, signed May 23, 2025 (90 FR 22591), directs the Secretary to create the pilot under the Atomic Energy Act’s authorization of reactors “under contract with and for the account of” DOE (42 U.S.C. 2140). It tells the Secretary to “approve at least three reactors” with “the goal of achieving criticality in each of the three reactors by July 4, 2026.”

How companies engage

DOE issued its Request for Applications, DE-FOA-0003569, on June 18, 2025. Initial applications closed July 21, 2025. Later applications are accepted on a rolling basis. Selection weighed technology readiness, site, financial viability and a plan to reach criticality.

Selections

On August 12, 2025, DOE selected 11 projects from 10 companies:

  • Aalo Atomics
  • Antares Nuclear
  • Atomic Alchemy
  • Deep Fission
  • Last Energy
  • Oklo (two projects)
  • Natura Resources
  • Radiant Industries
  • Terrestrial Energy
  • Valar Atomics

What happened by July 4, 2026

  • June 4. Antares Nuclear’s Mark-0 reached criticality at Idaho National Laboratory.
  • June 18. Valar Atomics’ Ward 250 reached criticality at the Utah San Rafael Energy Lab. DOE called it the “first DOE authorized reactor built outside of a national laboratory.”
  • June 30. Deployable Energy’s Unity reached criticality at Idaho National Laboratory under the Nuclear Energy Launch Pad, which DOE calls the pilot program’s successor. DOE said this met the President’s goal.
  • July 6. DOE announced that Aalo Atomics’ Aalo-X had reached criticality “early Saturday” at Idaho National Laboratory. It was the fourth DOE-authorized reactor to do so.

All four were zero-power criticality demonstrations. None of them generated electricity.

Since then, Oklo’s Groves Isotope Test Reactor in Lockhart, Texas reached criticality in early August 2026, the fifth DOE-authorized reactor to do so and the first on private land. On November 11, 2026, Oklo said DOE had cleared its final operations hold point.

What to watch

  • Whether EDF’s conditional commitments to the AP1000 supply chain, Vistra and Constellation reach financial close.
  • NRC approvals for the Palisades and Duane Arnold restarts, which their loans depend on.
  • EDF’s remaining section 1706 window, which runs through September 30, 2028.
  • A fourth HALEU allocation round, and when domestic commercial HALEU enrichment comes online.
  • Which pilot program reactors move from zero-power tests toward power operation or NRC licensing.

Operon tracks DOE solicitations, awards and loan actions in its briefings.

Primary sources

About this guide. Written from primary sources, each linked in the text. It describes the rules and programs; it is not legal advice. If something here is wrong or out of date, tell us and we will correct it with a dated note.